What is the Peripheral Ring Road (PRR) project?
It’s a 65 km stretch connecting Tumkur Road to Hosur road via Bellary road and Old Madras road. It runs around most of the perimeter of Bangalore city.
Why is this problematic?
33,838 trees in danger!
The Bangalore Development Authority (BDA) proposed Peripheral Ring Road (PRR) project nearly 3 years ago.
PRR project timeline:
BDA initially submitted an EIA report claiming that 200 trees will be cut
Horticulture and Forest department then submitted a contradicting report indicating that 16,685 trees will be felled
National Green Tribunal (NGT) notices this discrepancy and asks for the submission of a fresh EIA report
In June 2020, BDA submitted the revised EIA report that states 33,838 trees across 25 acres of forest land, and 6 water bodies will be under threat because of this project.
- In July 2020, the state government announced a public hearing on the PRR project in the midst of the Corona pandemic.
- The Public consultation scheduled for 11 am on August 18th at Nityotsava Kalyana Mantapa was called off by Minister of Environment, Anand Singh.
- Bangalore Development Authority (BDA) conducted a public hearing on August 11, flouting an order from the Minister of Environment.
- Virtual hearing scheduled for September 3 is postponed.
What are we asking for?
Provide the Detailed Project Report.
Conduct fresh EIA, based on exact details of the project.
Scrap the PRR project until fresh DPR and EIA report is provided.
Live tweets from Virtual PRR hearing
Close to 50,000 trees will be cut for upcoming road projects in Bangalore. Sign the petitions now to the future of our city. …@jhatkaadotorg #MaraKadiBedi #CancelPRR

Stop axing trees in Bengaluru | Air A!ert
8561 trees are proposed to be cut for a road-widening project, in order to decongest the tech corridor. More tha…
bit.ly
Close to 50,000 trees will be cut for upcoming road projects in Bangalore. Sign the petitions now to the future of our city. …http://bit.ly/2EvKlXu @jhatkaadotorg #MaraKadiBedi #CancelPRR
BDA had admitted to submitting old and faulty EIA report. How is BDA expecting citizens to trust the current EIA without DPR
#cancelPRR
…#PRRPublichearing
EIA is conducted only after project is finalised. How is BDA holding the process without valid DPR. #cancelPRR
#PRRPublichearing
The alignment goes through 19 wards of the BBMP but they have not been included in the EIA study. Therefore, the population count and tree… count is underestimated and the SIA is also incomplete.
#cancelPRR
#PRRPublichearing
It is public project worth 15,000+crores & 33,000+ trees cut, with impact on water bodies, catchment, forest, going over gas pipelines …AND change in alignment with increase of 40% in land acquisition! #cancelPRR
#PRRPublichearing
You can create the ecology of a area in other area. It has to be preserved where it is. #cancelPRR
#PRRPublichearing
I am 22 years old and I am really worried about the climate change and depletion of water resources that this project will cause. Can more …sustainable alternatives be explored before chopping of trees. #cancelPRR
#PRRPublichearing
Bangaloreans have no clarity on the compensatory afforestation which were promised for projects. Isn’t it better to do aforrestation before… cutting the trees. This is restore faith of public. #cancelPRR
#PRRPublichearing
Is there a place where we can see the final alignment for the #PRRproject #cancelPRR
#PRRPublichearing
Bengaluru has been dug up all over by smart City projects and metro, why not complete those works and then start new ones
#cancelPRR
…#PRRPublichearing
This is a massive project worth 15,000 crores. How can DPR not be shared? Should we not know what the government is coming up with?
…#cancelPRR
#PRRPublichearing
What’s need to have this public work during pandemic? #cancelPRR
#PRRPublichearing
This EIA is based on 1800+ acres land acquisition as per old alignment. BDA says additional 700+ acres to be acquired. That is 40% of …alignment change. How is this EIA valid? #cancelPRR
#PRRPublichearing
This project needs to be cancelled. 33,000 trees to go, several species of birds would be displaced.
#cancelPRR
#PRRPublichearing
New alignment changes calls for new EIA. Is this public consultation valid without DPR? We were asked by #BDAcommisssioner to give our …inputs using the third party audit (pollution control board), how this is possible?? #cancelPRR
#PRRPublichearing
In the draft commercial housing are mentioned but the cost of development is not mentioned the cost in the project. #cancelPRR
…#PRRPublichearing
Is this not in contravention of the NGT order with respect to lakes?
#cancelPRR
#PRRPublichearing
How can this project go ahead without the DPR being made public? Isn’t this project a public project?
#cancelPRR
#PRRPublichearing
DPR hasn’t been shared. EIA hasn’t been done for the revised plan. Several farmers, citizens and land owners have opposed the project. …Is BDA for citizens or just the real estate and political lobby?
#CancelPRR
DPR has not been provided publicly. In fact, not even ready due to change in alignment. #cancelPRR
#PRRPublichearing
BDA has announced alignment changes & additional 700+ acres to be acquired. How is this EIA valid?
#cancelPRR
#PRRPublichearing
ORR has got traffic-saturated within twenty years. How long will PRR take to get similarly saturated? Wouldn’t a circular railway line be a… better alternative? Also less land would be required.
#cancelPRR
#PRRPublichearing
#BDA does not answer the question of #PRRproject will reduce travel time. #cancelPRR
#PRRPublichearing
Suburban rail, Metro enhancement, mass rapid transportation, etc…please check other options for traffic congestion.
#cancelPRR
…#PRRPublichearing
#BDA continues to remain silent on the issue of the water development. They have no answer about it. #cancelPRR
#PRRPublichearing
How is the compensation decided for the #greenbelt for construction of the PRR project. #cancelPRR
#PRRPublichearing
Outer Ring Road is already having issues of immense traffic. How is BDA is going to ensure more traffic is not used in the city. …#cancelPRR
#PRRPublichearing
People Suggest scrap PRR and go for a circular Rail project, which would benefit more people in a more cost-effective manner? Land …requirement will also be less.
#cancelPRR
#PRRPublichearing
Even an eight-lane PRR would get traffic-saturated in fifteen years, so only a circular railway line would be a better alternative.
…#cancelPRR
#PRRPublichearing
How does traffic gain precedence over something as basic as water? This project is going to impact water depleted Bangalore. #cancelPRR
…#PRRPublichearing
The PRR project is illegal, not law abiding, anti-farmer and not sustainable. 33,000 trees would have to be felled for this, with loss of …habitat for several birds.
#CancelPRR
Citizens in the call are demanding for spending on ORR metro and public transport over PRR @srivasrbmrccoi1 @DULTBangalore and by now the overall tone of the conversation with 160 citizens is #cancelPRR We really hope the recording will be made available to the wider public https://twitter.com/citizenmatters/status/1308624437780963330
More than 12000 people are asking for DPR of the project. #BDA provided erroreneous EIA report how do they public to trust the current EIA?… http://bit.ly/3mMPUlR
#cancelPRR
#PRRPublichearing
More roads will attract more vehicles and traffic will become more. #cancelPRR
#PRRPublichearing
Wouldn’t a circular suburban railway line be a better and more cost-effective alternative, require less land and would also serve the needs… of mass transportation?
#cancelPRR
#PRRPublichearing
Why is #BDA not following due process and releasing the #DPR to the public? #cancelPRR
#PRRPublichearing
Bangalore is water stareved and the project is going to impact 6 lakes. TG reservoir primary source of water for Bengaluru’s residents. …How is #BDA accounting for the depleting water resources. #cancelPRR
#PRRPublichearing
Studies show that building roads only increases traffic . How will Bangalore accommodate more vehicles when it already has more than 85 …lakh vehicles http://bit.ly/3mNwM6W
#cancelPRR #savethetreesofbnagalore
#PRRPublichearing
There are serious concerns about PRR’s effects on the city’s almost-depleted green cover, its water bodies and biodiversity.
#cancelPRR… #savethetreesofbnagalore
#PRRPublichearing
What is the going to happen about the Bangalore water table. The project is going to impact the water starved Bangalore city. How is #BDA …going to compensate depleting water. #cancelPRR
#PRRPublichearing
Is a dedicated Bus lane (BRT) planned along the PRR? #cancelPRR #savethetreesofbnagalore
#PRRPublichearing
#marakadbedi, climate change is coming, development is important, but it has to be sustainable, this is wrong, PRR must be cancelled. …Innovative solutions must be explored, improve public transport
#cancelPRR
#PRRPublichearing
#BDA had submitted the wrong EIA report that project will impact 200 trees, how can trust you about afforestation or about compensation?
…#cancelPRR
#PRRPublichearing
What will b the financial burden on citizens of Bengaluru in terms of cess, tax etc to cover the cost of PRR?
#cancelPRR
#PRRPublichearing
#BDA suggests Rapid EIA for the #PRRproject. No point in commenting on Rapid EIA if it’s not comprehensive. This only shows the urgency …doesn’t build any confidence in the people which is the objective of public consultation.
#cancelPRR
#PRRPublichearing
How is BDA affording a 15000 crore project amidst huge financial crunch that the state is going through? http://bit.ly/33OUKGA
#cancelPRR …#savethetreesofbnagalore
#PRRPublichearing
More than 85 Lakh vehicles are on already on road is there any thought given to improving the public transport? Instead of the just …unsustainable road Development. #cancelPRR #savethetreesofbnagalore
#PRRPublichearing
#cancelPRR #savethetreesofbnagalore
#PRRPublicHearing What traffic analysis was done prior to initiating the PRR project. #KRDCL is coming …up new roads. All the roads except the Tumkur road has more than 5% heavy vehicle.
Citizens in the call are demanding for spending on ORR metro and public transport over PRR @srivasrbmrccoi1 @DULTBangalore and by now the …overall tone of the conversation with 160 citizens is #cancelPRR We really hope the recording will be made available to the wider public

The Bangalore Development Authority (BDA) and Karnataka State Pollution Control Board (KSPCB) are holding a virtual public hearing on Peripheral Ring road Project (PRR) today, Sept 23, at 11 AM on Zoom.
Massive respect to @leofsaldanha sir for ripping these guys. PRR is an illegal project conceptualised to help the real estate and political… lobby. It is an anti-farmer and anti-environment Project. This project must be cancelled!
#CancelPRR
BDA had admitted to submitting old and faulty EIA report. How is BDA expecting citizens to trust the current EIA without DPR
#cancelPRR
…#PRRPublichearing
EIA is conducted only after project is finalised. How is BDA holding the process without valid DPR. #cancelPRR
#PRRPublichearing
The alignment goes through 19 wards of the BBMP but they have not been included in the EIA study. Therefore, the population count and tree… count is underestimated and the SIA is also incomplete.
#cancelPRR
#PRRPublichearing
It is public project worth 15,000+crores & 33,000+ trees cut, with impact on water bodies, catchment, forest, going over gas pipelines …AND change in alignment with increase of 40% in land acquisition! #cancelPRR
#PRRPublichearing
You can create the ecology of a area in other area. It has to be preserved where it is. #cancelPRR
#PRRPublichearing
I am 22 years old and I am really worried about the climate change and depletion of water resources that this project will cause. Can more …sustainable alternatives be explored before chopping of trees. #cancelPRR
#PRRPublichearing
Bangaloreans have no clarity on the compensatory afforestation which were promised for projects. Isn’t it better to do aforrestation before… cutting the trees. This is restore faith of public. #cancelPRR
#PRRPublichearing
Is there a place where we can see the final alignment for the #PRRproject #cancelPRR
#PRRPublichearing
Bengaluru has been dug up all over by smart City projects and metro, why not complete those works and then start new ones
#cancelPRR
…#PRRPublichearing
This is a massive project worth 15,000 crores. How can DPR not be shared? Should we not know what the government is coming up with?
…#cancelPRR
#PRRPublichearing
What’s need to have this public work during pandemic? #cancelPRR
#PRRPublichearing
This EIA is based on 1800+ acres land acquisition as per old alignment. BDA says additional 700+ acres to be acquired. That is 40% of …alignment change. How is this EIA valid? #cancelPRR
#PRRPublichearing
This project needs to be cancelled. 33,000 trees to go, several species of birds would be displaced.
#cancelPRR
#PRRPublichearing
New alignment changes calls for new EIA. Is this public consultation valid without DPR? We were asked by #BDAcommisssioner to give our …inputs using the third party audit (pollution control board), how this is possible?? #cancelPRR
#PRRPublichearing
In the draft commercial housing are mentioned but the cost of development is not mentioned the cost in the project. #cancelPRR
…#PRRPublichearing
Is this not in contravention of the NGT order with respect to lakes?
#cancelPRR
#PRRPublichearing
How can this project go ahead without the DPR being made public? Isn’t this project a public project?
#cancelPRR
#PRRPublichearing
DPR has not been provided publicly. In fact, not even ready due to change in alignment. #cancelPRR
#PRRPublichearing
BDA has announced alignment changes & additional 700+ acres to be acquired. How is this EIA valid?
#cancelPRR
#PRRPublichearing
ORR has got traffic-saturated within twenty years. How long will PRR take to get similarly saturated? Wouldn’t a circular railway line be a… better alternative? Also less land would be required.
#cancelPRR
#PRRPublichearing
#BDA does not answer the question of #PRRproject will reduce travel time. #cancelPRR
#PRRPublichearing
Suburban rail, Metro enhancement, mass rapid transportation, etc…please check other options for traffic congestion.
#cancelPRR
…#PRRPublichearing
#BDA continues to remain silent on the issue of the water development. They have no answer about it. #cancelPRR
#PRRPublichearing
How is the compensation decided for the #greenbelt for construction of the PRR project. #cancelPRR
#PRRPublichearing
Outer Ring Road is already having issues of immense traffic. How is BDA is going to ensure more traffic is not used in the city. …#cancelPRR
#PRRPublichearing
People Suggest scrap PRR and go for a circular Rail project, which would benefit more people in a more cost-effective manner? Land …requirement will also be less.
#cancelPRR
#PRRPublichearing
Even an eight-lane PRR would get traffic-saturated in fifteen years, so only a circular railway line would be a better alternative.
…#cancelPRR
#PRRPublichearing
How does traffic gain precedence over something as basic as water? This project is going to impact water depleted Bangalore. #cancelPRR
…#PRRPublichearing
More than 12000 people are asking for DPR of the project. #BDA provided erroreneous EIA report how do they public to trust the current EIA?… http://bit.ly/3mMPUlR
#cancelPRR
#PRRPublichearing
More roads will attract more vehicles and traffic will become more. #cancelPRR
#PRRPublichearing
Wouldn’t a circular suburban railway line be a better and more cost-effective alternative, require less land and would also serve the needs… of mass transportation?
#cancelPRR
#PRRPublichearing
Why is #BDA not following due process and releasing the #DPR to the public? #cancelPRR
#PRRPublichearing
Bangalore is water stareved and the project is going to impact 6 lakes. TG reservoir primary source of water for Bengaluru’s residents. …How is #BDA accounting for the depleting water resources. #cancelPRR
#PRRPublichearing
Studies show that building roads only increases traffic . How will Bangalore accommodate more vehicles when it already has more than 85 …lakh vehicles http://bit.ly/3mNwM6W
#cancelPRR #savethetreesofbnagalore
#PRRPublichearing
There are serious concerns about PRR’s effects on the city’s almost-depleted green cover, its water bodies and biodiversity.
#cancelPRR… #savethetreesofbnagalore
#PRRPublichearing
What is the going to happen about the Bangalore water table. The project is going to impact the water starved Bangalore city. How is #BDA …going to compensate depleting water. #cancelPRR
#PRRPublichearing
Is a dedicated Bus lane (BRT) planned along the PRR? #cancelPRR #savethetreesofbnagalore
#PRRPublichearing
#marakadbedi, climate change is coming, development is important, but it has to be sustainable, this is wrong, PRR must be cancelled. …Innovative solutions must be explored, improve public transport
#cancelPRR
#PRRPublichearing
#BDA had submitted the wrong EIA report that project will impact 200 trees, how can trust you about afforestation or about compensation?
…#cancelPRR
#PRRPublichearing
What will b the financial burden on citizens of Bengaluru in terms of cess, tax etc to cover the cost of PRR?
#cancelPRR
#PRRPublichearing
#BDA suggests Rapid EIA for the #PRRproject. No point in commenting on Rapid EIA if it’s not comprehensive. This only shows the urgency …doesn’t build any confidence in the people which is the objective of public consultation.
#cancelPRR
#PRRPublichearing
How is BDA affording a 15000 crore project amidst huge financial crunch that the state is going through? http://bit.ly/33OUKGA
#cancelPRR …#savethetreesofbnagalore
#PRRPublichearing
More than 85 Lakh vehicles are on already on road is there any thought given to improving the public transport? Instead of the just …unsustainable road Development. #cancelPRR #savethetreesofbnagalore
#PRRPublichearing
#cancelPRR #savethetreesofbnagalore
#PRRPublicHearing What traffic analysis was done prior to initiating the PRR project. #KRDCL is coming …up new roads. All the roads except the Tumkur road has more than 5% heavy vehicle.
#PRRPublichearing How will #BDA ensure TG Halli reservoir is not destroyed? This is an eyewash. How will you ensure that Ground water …levels are not affected? – ongoing hearing
#PRRpublichearing Construction of the PRR would involve the loss of 10 hectares (25 acres) of forested land in Jarakabandekaval Reserve …Forest.
#PRRPublicHearing The DPR is still not releases and the Bangalore Public is finding it difficult to assess the impact of the project.
What you can do?
Jhatkaa.org has prepared a template message with topline concerns. Feel free to add more suggestions when sending the response. Last date of sending response via email is 15 September 2020. With a single click email will be sent to KSPCB, BDA and Deputy Commissioner Bangalore Urban
Dates for virtual hearing
1. Meeting on 23 September 2020 at 11 am.
Medium Zoom
Meeting id – 850 1729 9310
Passcode-bpe2020

Concerns to be raised during public hearing
Environmental concerns
- Felling of 33,838 trees will be a gigantic loss to the environment of Bengaluru. The initial Environment Impact Assessment (EIA) was deemed erroneous and rejected by the National Green Tribunal. As in the initial report, it was suggested that only 200 trees will be impacted.
- A 100-metre road in a forest area is highly detrimental to wildlife and should not be allowed, it can be detrimental to wildlife in the near vicinity.
- PRR is passing along and going over 6 lakes. Bangalore urban district is highly deficient in water, and building the PRR road would further exacerbate the problem. When facing gross groundwater deficiency with resources already overexploited, water resources would be further stressed by having a Ring Road which will greatly exacerbate the problem.
- The Thippagondanahalli reservoir will be irretrievably damaged by the prr going through it and the attempts of the government to restore it will be severely compromised.
Socio-economic concerns
- The Ring Road alignment has been changed since the initial project report and therefore this project should be rendered as a new project under the Karnataka Town Planning Act
- The current EIA report lacks clarity on the compensation to be given to people loosing land. Details of rehabilitation and relocation are not clear. Moreover, the compensation per individual land loser per village is not given.
- Close to one million people are likely to be impacted by the project.In the current times when COVID cases are on the rise, many people may not be able to participate in public consultations. A number of people may not have access to the internet and therefore cannot participate in the public hearing process.
- The Report states that 1451 structures will be impacted but it does not give the location village-wise of these structures. Since the project has been delayed by 15 years, the BDA officials had themselves told us that 2/3rd of the alignment is built up. Tearing down these structures may lead to a law and order problem. Show of brute force by the government will not go down with the people.
Demand
Scrap the PRR project until fresh DPR and EIA is provided.
ಪೆರಿಫೆರೆಲ್ ರಿಂಗ ರಸ್ತೆ ಯೋಜನೆಯ DPR ಇಲ್ಲದೆ ಸಾರ್ವಜನಿಕ ಸಮಾಲೋಚನೆ ಹೇಗೆ ಮಾಡ್ತೀರ BDAಯವರೆ?
@CMofKarnataka @NGTribunal @Jhatkaadotorg
bit.ly/3gNThoi
#PRR #DPRಎಲ್ಲಿ #DPRತೋರಿಸಿ #DPR_torisi #DPR_yelli
DPR ತಾಯರಿಲ್ಲದೆ ಪೆರಿಫೆರೆಲ್ ರಿಂಗ್ ರಸ್ತೆಯ ಸಮಾಲೋಚನೆಗೆ ಸಾರ್ವಜನಿಕರನ್ನ ಕರೆದರೆ ಏನು ಪ್ರಯೋಜನ? ಮೊದಲುDPR_ತೋರಿಸಿ ನಂತರ ಸಮಾಲೋಚನೆಗೆ ಕರೆಯಿರಿ. bit.ly/3gNThoi @CMofKarnataka @NGTribunal @Jhatkaadotorg
#PRR #DPRಎಲ್ಲಿ #DPRತೋರಿಸಿ #DPR_torisi #DPR_yelli
The BDA had falsely claimed that just 200 trees will be felled for the PRR project. Send a message bit.ly/3gNThoi demanding that they are held accountable for this erroneous EIA report. @CMofKarnataka @NGTribunal @Jhatkaadotorg
The BDA had falsely claimed that just 200 trees will be felled for the PRR project. Send a message bit.ly/3gNThoi demanding that they be held accountable for this erroneous EIA report. @CMofKarnataka @NGTribunal @Jhatkaadotorg